Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Jan 23, 2026

THIS WEEK'S ACCOMPLISHMENT

    Began hanging ductwork and mechanical indoor units on L-1.
    Continued all MEP OH rough-in on L-1.
    Began installing new fencing around WQ Pond and new sidewalk for PR06.
    Continued working on L-2 structural steel.
    Began installing shaft liner on exterior walls on L-1.
Excavation 1.jpg

Shaft liner beginning to be installed on L-1.

NEXT WEEK'S ACTIVITIES

    Start all new roofing work on L-2.
    Continue working on all MEP OH rough-in on L-1.
    Continue putting up shaft liner and sheathing on exterior walls on L-1.
    Layout interior & exterior walls on L-2.
    Start transitioning MEP OH rough-in & layout from L-1 to L-2.
Excavation 1.jpg

Ductwork started being installed.

Excavation 1.jpg

L-2 structural steel final weld up.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.