Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Jan 23, 2026
THIS WEEK'S ACCOMPLISHMENT
- Began hanging ductwork and mechanical indoor units on L-1.
- Continued all MEP OH rough-in on L-1.
- Began installing new fencing around WQ Pond and new sidewalk for PR06.
- Continued working on L-2 structural steel.
- Began installing shaft liner on exterior walls on L-1.
-

Shaft liner beginning to be installed on L-1.
NEXT WEEK'S ACTIVITIES
- Start all new roofing work on L-2.
- Continue working on all MEP OH rough-in on L-1.
- Continue putting up shaft liner and sheathing on exterior walls on L-1.
- Layout interior & exterior walls on L-2.
- Start transitioning MEP OH rough-in & layout from L-1 to L-2.

-
Ductwork started being installed.

L-2 structural steel final weld up.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.