top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Jul 3, 2025

THIS WEEK'S ACCOMPLISHMENT

    Continued Trenching for SS-A as well as Demo of the Existing Storm Sewer
    Continued Grading on the Detention Pond, as well as installing Road Base in the new Parking Spaces
    Had Pre-Construction Meetings with Raba Kistner, Texas Roofing, Wolff Construction, and Kinney's Commercial Inc
    Manholes / Junction Boxes were Delivered on Site
    Continued Digging on Water Quality Pond #2
    Completed Wire Pull to the First Floor Electrical Room
Excavation 1.jpg

Detention Pond Grading and Spoil Haul-Off

NEXT WEEK'S ACTIVITIES

    Have our required Pre-Construction meeting with WCID-17 and LTFR on Monday.
    Continue Grading on the Detention Pond
    Continue Trench for SS-A, as well as Demo on the Existing Storm Sewer
    Start Grading Water Quality Pond #2
    Have our Water Quality Pond Pre-Construction Meeting with LCRA and Travis County on Tuesday
Excavation 1.jpg
    Start FRP of New Curbs on the Bus Loop

Parking Lot Grading and Road Base

Excavation 1.jpg

Storm Sewer Line A Trench

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page