top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Jul 3, 2025
THIS WEEK'S ACCOMPLISHMENT
- Continued Trenching for SS-A as well as Demo of the Existing Storm Sewer
- Continued Grading on the Detention Pond, as well as installing Road Base in the new Parking Spaces
- Had Pre-Construction Meetings with Raba Kistner, Texas Roofing, Wolff Construction, and Kinney's Commercial Inc
- Manholes / Junction Boxes were Delivered on Site
- Continued Digging on Water Quality Pond #2
- Completed Wire Pull to the First Floor Electrical Room

Detention Pond Grading and Spoil Haul-Off
NEXT WEEK'S ACTIVITIES
- Have our required Pre-Construction meeting with WCID-17 and LTFR on Monday.
- Continue Grading on the Detention Pond
- Continue Trench for SS-A, as well as Demo on the Existing Storm Sewer
- Start Grading Water Quality Pond #2
- Have our Water Quality Pond Pre-Construction Meeting with LCRA and Travis County on Tuesday

- Start FRP of New Curbs on the Bus Loop
Parking Lot Grading and Road Base

Storm Sewer Line A Trench
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.