top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Oct 17, 2025
THIS WEEK'S ACCOMPLISHMENT
- Placed 160yds of SOG in Area A.
- Continued underground MEP Rough-In in Area B.
- Began excavating grade beams in Area B.
- Placed two more Poured Form Finish columns.
- Continued FRP for walls in Area B.
-

Placement of SOG A
NEXT WEEK'S ACTIVITIES
- Place remaining grade beams in Area B.
- Place walls in Area B.
- Continue MEP Rough-In in Area B.
- Preconstruction meeting for structural steel.
-

-
Placement of SOG A

Finish of SOG A
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page