THIS WEEK'S ACCOMPLISHMENT

    Placed 160yds of SOG in Area A.
    Continued underground MEP Rough-In in Area B.
    Began excavating grade beams in Area B.
    Placed two more Poured Form Finish columns.
    Continued FRP for walls in Area B.
Excavation 1.jpg

Placement of SOG A

NEXT WEEK'S ACTIVITIES

    Place remaining grade beams in Area B.
    Place walls in Area B.
    Continue MEP Rough-In in Area B.
    Preconstruction meeting for structural steel.
Excavation 1.jpg

Placement of SOG A

Excavation 1.jpg

Finish of SOG A

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.