THIS WEEK'S ACCOMPLISHMENT

    FRP Curbs, Sidewalk, and Dumpster Pad at the Bus Loop
    Two 3x3 Grate Inlets and RCP Install at the Bus Loop
    Roof Drain Flood Test and Domestic Water Inspection
    Required Pre-Construction Meeting with LTFR
    Started Asphalt Demo in the Bus Loop
    Started Backfilling Trench for SS-A
Excavation 1.jpg

Asphalt Demo at the Bus Loop

NEXT WEEK'S ACTIVITIES

    Complete Phase One Water and Roof Drain Pipe Insulation
    FRP Concrete Flume and 24" Headwall at the Bus Loop
    Working on Sub-Grade on the Bus Loop Road and Parking Areas
    Mobilize B&L to repair any disturbed areas in the Existing Building
    Complete Fire Caulking for any Electrical Penetrations
Excavation 1.jpg
    Continue Install and Back SS-A for Paving

Junction Box, Manhole, and Grate Inlet Install at SS-A

Excavation 1.jpg

FRP Laydown and Sawtooth Curbs at the Bus Loop