Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Jul 19, 2025
THIS WEEK'S ACCOMPLISHMENT
- FRP Curbs, Sidewalk, and Dumpster Pad at the Bus Loop
- Two 3x3 Grate Inlets and RCP Install at the Bus Loop
- Roof Drain Flood Test and Domestic Water Inspection
- Required Pre-Construction Meeting with LTFR
- Started Asphalt Demo in the Bus Loop
- Started Backfilling Trench for SS-A

Asphalt Demo at the Bus Loop
NEXT WEEK'S ACTIVITIES
- Complete Phase One Water and Roof Drain Pipe Insulation
- FRP Concrete Flume and 24" Headwall at the Bus Loop
- Working on Sub-Grade on the Bus Loop Road and Parking Areas
- Mobilize B&L to repair any disturbed areas in the Existing Building
- Complete Fire Caulking for any Electrical Penetrations

- Continue Install and Back SS-A for Paving
Junction Box, Manhole, and Grate Inlet Install at SS-A

FRP Laydown and Sawtooth Curbs at the Bus Loop
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.