top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Aug 8, 2025
THIS WEEK'S ACCOMPLISHMENT
- Paved Exit Lane on Spillman Loop
- Striped the Bus Loop, New Parking Areas, and Exit Lane on Spillman Loop
- Installed Water Barricades and Fence Panels
- Reworked Existing Sanitary Sewer Manhole Inverts, Completed Installation of New Sanitary Pipe
- Completed all Work in the Existing Building. Ready for First Day of School
- Continued installation on Storm Sewer Line SS-A

SS-A Progress
NEXT WEEK'S ACTIVITIES
- Conduct a Water Shutdown, and Tie-In Water Line WL-A
- Continue Excavating the Building Foundation, and Installing Base Material.
- Open One Lane of Spillman Loop for School Start
- Continue Digging and Backfilling Storm Sewer Line SS-A Crossing Lot P10
- Meet with LTFR, Install all Necessary Exit Signs and Turn over the High School back to LTHS

- Turn over the Bus Loop to LTHS
New Striping

One Lane Of Spillman Loop and Water Barricades
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page