Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Aug 8, 2025

THIS WEEK'S ACCOMPLISHMENT

    Paved Exit Lane on Spillman Loop
    Striped the Bus Loop, New Parking Areas, and Exit Lane on Spillman Loop
    Installed Water Barricades and Fence Panels
    Reworked Existing Sanitary Sewer Manhole Inverts, Completed Installation of New Sanitary Pipe
    Completed all Work in the Existing Building. Ready for First Day of School
    Continued installation on Storm Sewer Line SS-A
Excavation 1.jpg

SS-A Progress

NEXT WEEK'S ACTIVITIES

    Conduct a Water Shutdown, and Tie-In Water Line WL-A
    Continue Excavating the Building Foundation, and Installing Base Material.
    Open One Lane of Spillman Loop for School Start
    Continue Digging and Backfilling Storm Sewer Line SS-A Crossing Lot P10
    Meet with LTFR, Install all Necessary Exit Signs and Turn over the High School back to LTHS
Excavation 1.jpg
    Turn over the Bus Loop to LTHS

New Striping

Excavation 1.jpg

One Lane Of Spillman Loop and Water Barricades

LOOK AHEAD SCHEDULE