top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Sep 5, 2025
THIS WEEK'S ACCOMPLISHMENT
- Drilled and placed 26 more piers this week.
- Began working on excavating grade beams.
- Continued to lay pipe and backfill Storm System Line near Water Quality Pond #2.
-
-
-

Storm System Line in place near Water Quality Pond #2
NEXT WEEK'S ACTIVITIES
- Continue to excavate grade beams.
- Finish up pier drilling and placing.
- Begin Electrical and Plumbing rough-in.
- Continue to work on Water Quality Ponds.
-

-
Excavation of grade beams started

Pier operations continuing
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page