Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Sep 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    Drilled and placed 26 more piers this week.
    Began working on excavating grade beams.
    Continued to lay pipe and backfill Storm System Line near Water Quality Pond #2.
Excavation 1.jpg

Storm System Line in place near Water Quality Pond #2

NEXT WEEK'S ACTIVITIES

    Continue to excavate grade beams.
    Finish up pier drilling and placing.
    Begin Electrical and Plumbing rough-in.
    Continue to work on Water Quality Ponds.
Excavation 1.jpg

Excavation of grade beams started

Excavation 1.jpg

Pier operations continuing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.