top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Dec 5, 2025
THIS WEEK'S ACCOMPLISHMENT
- Placed PR06 sidewalk.
- Began installation of metal decking for L-2 slab.
- Weld-Up inspections passed.
- Inspection for UG electrical conduit for power from existing building passed.
- Nelson studs installed on L-2 metal decking.
- Began layout for L-1 OH MEP rough-in.

Start of L-2 metal decking installation
NEXT WEEK'S ACTIVITIES
- Complete L-2 metal decking.
- FRP L-2 slab on metal deck.
- Begin layout for interior walls on L-1.
- Start work on the CMU wall for the elevator.
- Begin FRP for L-2 concrete walls and columns.

-
Sidewalk for PR06 placed

L-2 metal decking for slab
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page