Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Dec 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    Placed PR06 sidewalk.
    Began installation of metal decking for L-2 slab.
    Weld-Up inspections passed.
    Inspection for UG electrical conduit for power from existing building passed.
    Nelson studs installed on L-2 metal decking.
    Began layout for L-1 OH MEP rough-in.
Excavation 1.jpg

Start of L-2 metal decking installation

NEXT WEEK'S ACTIVITIES

    Complete L-2 metal decking.
    FRP L-2 slab on metal deck.
    Begin layout for interior walls on L-1.
    Start work on the CMU wall for the elevator.
    Begin FRP for L-2 concrete walls and columns.
Excavation 1.jpg

Sidewalk for PR06 placed

Excavation 1.jpg

L-2 metal decking for slab

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.