top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Aug 22, 2025
THIS WEEK'S ACCOMPLISHMENT
- Completed Excavation of the Building Foundation
- Began Tying Rebar for Drilled Piers
- Held a Pre-Construction Meeting with Raba Kistner, Wolff Construction, and Drillers to coordinate Drilled Piers Operation
- Crossed Lot P10 with Storm Sewer Line SS-A, Set the Curb Inlet and Manhole by WQ #2
- Poured Board Form Concrete Plinth Mock-Up
- Laid out Drilled Pier Locations and Building Corners

SS-A Progress Through Lot P10
NEXT WEEK'S ACTIVITIES
- Begin Drilled Pier Operation Next Tuesday
- Install 5x5 Box and Pipe in the Detention Pond
- Demo Existing Storm Sewer Line in Water Quality Pond #2
-
-

-
Rebar Cages for Drilled Piers

Building Foundation Pad
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page