Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Aug 22, 2025

THIS WEEK'S ACCOMPLISHMENT

    Completed Excavation of the Building Foundation
    Began Tying Rebar for Drilled Piers
    Held a Pre-Construction Meeting with Raba Kistner, Wolff Construction, and Drillers to coordinate Drilled Piers Operation
    Crossed Lot P10 with Storm Sewer Line SS-A, Set the Curb Inlet and Manhole by WQ #2
    Poured Board Form Concrete Plinth Mock-Up
    Laid out Drilled Pier Locations and Building Corners
Excavation 1.jpg

SS-A Progress Through Lot P10

NEXT WEEK'S ACTIVITIES

    Begin Drilled Pier Operation Next Tuesday
    Install 5x5 Box and Pipe in the Detention Pond
    Demo Existing Storm Sewer Line in Water Quality Pond #2
Excavation 1.jpg

Rebar Cages for Drilled Piers

Excavation 1.jpg

Building Foundation Pad

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.