Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Sep 19, 2025

THIS WEEK'S ACCOMPLISHMENT

    Rebar was onsite and tied in grade beam locations for our first placement.
    Placed 100yds of grade beams, including the elevator pit.
    Began laying out exterior walls on grade beams.
    Continued our underground plumbing rough-in.
    Continued work on the water quality pond and detention pond.
    Conducted a Weekly Progress Meeting onsite with the team.
Excavation 1.jpg

Work continuing in Water Quality Pond #2

NEXT WEEK'S ACTIVITIES

    Water quality pond concrete work.
    Underground electrical rough-in to begin.
    Embeds for columns delivered.
    Inspection & Testing for underground plumbing rough-in.
    First column and elevator pit walls placed.
Excavation 1.jpg
    Continue work on detention pond #1.

Rebar being tied in grade beams

Excavation 1.jpg

100yds of grade beams/elevator pit placed

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.