Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Sep 19, 2025
THIS WEEK'S ACCOMPLISHMENT
- Rebar was onsite and tied in grade beam locations for our first placement.
- Placed 100yds of grade beams, including the elevator pit.
- Began laying out exterior walls on grade beams.
- Continued our underground plumbing rough-in.
- Continued work on the water quality pond and detention pond.
- Conducted a Weekly Progress Meeting onsite with the team.

Work continuing in Water Quality Pond #2
NEXT WEEK'S ACTIVITIES
- Water quality pond concrete work.
- Underground electrical rough-in to begin.
- Embeds for columns delivered.
- Inspection & Testing for underground plumbing rough-in.
- First column and elevator pit walls placed.

- Continue work on detention pond #1.
Rebar being tied in grade beams

100yds of grade beams/elevator pit placed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.