top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Nov 7, 2025
THIS WEEK'S ACCOMPLISHMENT
- Placed final grade beam in Level 1.
- Placed Board Form Finish Wall in Area A.
- Oil Separator was delivered and set in its location.
- Began waterproofing on exterior walls.
- Continued FRP For Level 1 walls and columns.
-

Waterproofing on exterior walls started
NEXT WEEK'S ACTIVITIES
- Continue FRP for Level 1 walls and columns.
- Begin Re-Vegetation in bus loop area and detention pond/water quality pond.
- Begin PR06 scope.
- Begin Level 1 steel.
- Install Frech Drain system and Roof Drain tie-in.

-
Continued work for FRP on Level 1 walls and columns

Board Form Finish wall at the elevator for Level 1
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page