Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Nov 7, 2025

THIS WEEK'S ACCOMPLISHMENT

    Placed final grade beam in Level 1.
    Placed Board Form Finish Wall in Area A.
    Oil Separator was delivered and set in its location.
    Began waterproofing on exterior walls.
    Continued FRP For Level 1 walls and columns.
Excavation 1.jpg

Waterproofing on exterior walls started

NEXT WEEK'S ACTIVITIES

    Continue FRP for Level 1 walls and columns.
    Begin Re-Vegetation in bus loop area and detention pond/water quality pond.
    Begin PR06 scope.
    Begin Level 1 steel.
    Install Frech Drain system and Roof Drain tie-in.
Excavation 1.jpg

Continued work for FRP on Level 1 walls and columns

Excavation 1.jpg

Board Form Finish wall at the elevator for Level 1

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.