Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Aug 15, 2025

THIS WEEK'S ACCOMPLISHMENT

    Conducted a Water Shut Down and Tie-In, Tuesday at 4:00 AM
    Completed Summer Critical Work, and Opened one day before School Return Wednesday
    All Emergency Signage Installed and Approved by LTFR in the Existing Building
    Continued Installing Storm Sewer Line SS-A Crossing Lot P10
    Completed Demo on the Existing Water Line
    Continued Excavating for the Building Foundation, and Installing Base Material
Excavation 1.jpg

New Waterline Tie-In

NEXT WEEK'S ACTIVITIES

    Complete Excavation for the Building Foundation, and Installing Base Material
    Start Layout for Drilled Piers
    Continue Installing Storm Sewer Line SS-A Crossing through Lot P10
    Maintain Site Safety / Security for All. (Bus Loop Access)
Excavation 1.jpg

Building Pad Progress

Excavation 1.jpg

Site Progress Picture

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.