Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Aug 15, 2025
THIS WEEK'S ACCOMPLISHMENT
- Conducted a Water Shut Down and Tie-In, Tuesday at 4:00 AM
- Completed Summer Critical Work, and Opened one day before School Return Wednesday
- All Emergency Signage Installed and Approved by LTFR in the Existing Building
- Continued Installing Storm Sewer Line SS-A Crossing Lot P10
- Completed Demo on the Existing Water Line
- Continued Excavating for the Building Foundation, and Installing Base Material

New Waterline Tie-In
NEXT WEEK'S ACTIVITIES
- Complete Excavation for the Building Foundation, and Installing Base Material
- Start Layout for Drilled Piers
- Continue Installing Storm Sewer Line SS-A Crossing through Lot P10
- Maintain Site Safety / Security for All. (Bus Loop Access)
-

-
Building Pad Progress

Site Progress Picture
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.