Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Jan 9, 2026
THIS WEEK'S ACCOMPLISHMENT
- Started Hydromulching in both ponds and around the bus loop.
- Placed 3 Board Form Finish columnms and the wall in Area A.
- Started FRP on the final 3 Board From Finish columns on L-2.
- Began L-2 structural steel.
- Contniued L-1 interior and exterior wall framing.
- Continued L-1 MEP overhead Rough-In.

Exterior framing started.
NEXT WEEK'S ACTIVITIES
- Place final 3 Board Form Finish columns on L-2.
- Continue L-2 structural steel.
- Continue interior and exterior wall framing.
- Contniue all MEP overhead rough-in.
- IT/Low Voltage coordination metting.

-
Started L-2 structural steel.

Placed Board Form Finish wall on L-2.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.