Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Jan 9, 2026

THIS WEEK'S ACCOMPLISHMENT

    Started Hydromulching in both ponds and around the bus loop.
    Placed 3 Board Form Finish columnms and the wall in Area A.
    Started FRP on the final 3 Board From Finish columns on L-2.
    Began L-2 structural steel.
    Contniued L-1 interior and exterior wall framing.
    Continued L-1 MEP overhead Rough-In.
Excavation 1.jpg

Exterior framing started.

NEXT WEEK'S ACTIVITIES

    Place final 3 Board Form Finish columns on L-2.
    Continue L-2 structural steel.
    Continue interior and exterior wall framing.
    Contniue all MEP overhead rough-in.
    IT/Low Voltage coordination metting.
Excavation 1.jpg

Started L-2 structural steel.

Excavation 1.jpg

Placed Board Form Finish wall on L-2.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.