THIS WEEK'S ACCOMPLISHMENT
- Continued Grading the Detention Pond and Water Quality Pond #2
- Graded All Parking Areas
- Demoed the Existing Dumpster Pad
- Tied-In Wiring to the Existing Gear in the First Floor Electrical Room
- Concrete Forms for Bus Loop Parking Areas and Other Site Concrete
- Had our Required Pre-Construction Meeting with WCID-17

Electrical Shutdown, Tying into the Existing Gear.
NEXT WEEK'S ACTIVITIES
- Finish Hauling Off All Dirt From the Detention Pond
- Install Storm Drain at the Bus Loop
- Working on Concrete, "FRP" for the Bus Loop Curbs
- Backfilling Storm Drain on Spillman Loop
- Completing New Primary and Secondary Roof Drains in Existing Building

- "FRP" Bus Loop Dumpster Pad
On-Going Site Work

Bus Loop Curb Concrete Forms