THIS WEEK'S ACCOMPLISHMENT

    Continued Grading the Detention Pond and Water Quality Pond #2
    Graded All Parking Areas
    Demoed the Existing Dumpster Pad
    Tied-In Wiring to the Existing Gear in the First Floor Electrical Room
    Concrete Forms for Bus Loop Parking Areas and Other Site Concrete
    Had our Required Pre-Construction Meeting with WCID-17
Excavation 1.jpg

Electrical Shutdown, Tying into the Existing Gear.

NEXT WEEK'S ACTIVITIES

    Finish Hauling Off All Dirt From the Detention Pond
    Install Storm Drain at the Bus Loop
    Working on Concrete, "FRP" for the Bus Loop Curbs
    Backfilling Storm Drain on Spillman Loop
    Completing New Primary and Secondary Roof Drains in Existing Building
Excavation 1.jpg
    "FRP" Bus Loop Dumpster Pad

On-Going Site Work

Excavation 1.jpg

Bus Loop Curb Concrete Forms

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page