Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Aug 29, 2025
THIS WEEK'S ACCOMPLISHMENT
- Began operations for drilling and placing piers
- Continued working on the remaining storm sewer line that was left to do
- Demolition on existing storm line was started
- Drilled and placed 22 piers this week
- Installed phase one of new fencing plan. (LTHS, pedestrian access to auditorium)
-

Demolition of existing storm line
NEXT WEEK'S ACTIVITIES
- Continue all working operations for piers
- Continue all work on Water Quality Pond #2
- Continue work on bus loop pond
- OAC Thursday, September 4th, at 10:00AM
-

-
Drilling of Piers started

Placement of 22 piers this week
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.