THIS WEEK'S ACCOMPLISHMENT

    Began operations for drilling and placing piers
    Continued working on the remaining storm sewer line that was left to do
    Demolition on existing storm line was started
    Drilled and placed 22 piers this week
    Installed phase one of new fencing plan. (LTHS, pedestrian access to auditorium)
Excavation 1.jpg

Demolition of existing storm line

NEXT WEEK'S ACTIVITIES

    Continue all working operations for piers
    Continue all work on Water Quality Pond #2
    Continue work on bus loop pond