Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Nov 14, 2025

THIS WEEK'S ACCOMPLISHMENT

    Officially started going vertical with structural steel.
    Oil separator passed testing.
    Placed remaining Board Form Finish walls and columns for Level-1.
    Began installing French drain and roof drain connections.
    Continued working on LCRA punch list items.
    Continued waterproofing exterior walls.
Excavation 1.jpg

French drain installation

NEXT WEEK'S ACTIVITIES

    Continue setting structural steel columns and beams.
    Continue working on PR06.
    Continue completing LCRA punch list items for WQ #2, Detention Pond 1 and Bus Loop area.
    Continue waterproofing exterior walls.
    Continue installing French drain and roof drain connections.
Excavation 1.jpg

First steel column being set

Excavation 1.jpg

Structural steel progress

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.