Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Nov 14, 2025
THIS WEEK'S ACCOMPLISHMENT
- Officially started going vertical with structural steel.
- Oil separator passed testing.
- Placed remaining Board Form Finish walls and columns for Level-1.
- Began installing French drain and roof drain connections.
- Continued working on LCRA punch list items.
- Continued waterproofing exterior walls.

French drain installation
NEXT WEEK'S ACTIVITIES
- Continue setting structural steel columns and beams.
- Continue working on PR06.
- Continue completing LCRA punch list items for WQ #2, Detention Pond 1 and Bus Loop area.
- Continue waterproofing exterior walls.
- Continue installing French drain and roof drain connections.

-
First steel column being set

Structural steel progress
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.