top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Jan 2, 2026
THIS WEEK'S ACCOMPLISHMENT
- Roof drain overflow pipe being installed.
- All MEP OH rough-in continued.
- L-2 Board Form Finish columns and wall forms set.
- Re-Vegetation continued and temporary irrigation installed in all ponds and bus loop areas.
- Continued interior wall framing for L-1.
- L-1 hollow metal frames delivered onsite.

L-2 Board Form Finish concrete FRP.
NEXT WEEK'S ACTIVITIES
- Start Hydromulching in ponds and bus loop areas.
- Place remaining Board Form Finish walls and columns on L-2.
- Continue all OH MEP rough-in on L-1.
- Begin exterior wall framing on L-1.
- Begin L-2 structural steel.

- Continue OH fire suppression rough-in.
OH fire suppression rough-in.

Interior wall framing progress.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page