THIS WEEK'S ACCOMPLISHMENT

    Roof drain overflow pipe being installed.
    All MEP OH rough-in continued.
    L-2 Board Form Finish columns and wall forms set.
    Re-Vegetation continued and temporary irrigation installed in all ponds and bus loop areas.
    Continued interior wall framing for L-1.
    L-1 hollow metal frames delivered onsite.
Excavation 1.jpg

L-2 Board Form Finish concrete FRP.

NEXT WEEK'S ACTIVITIES

    Start Hydromulching in ponds and bus loop areas.
    Place remaining Board Form Finish walls and columns on L-2.
    Continue all OH MEP rough-in on L-1.
    Begin exterior wall framing on L-1.
    Begin L-2 structural steel.
Excavation 1.jpg
    Continue OH fire suppression rough-in.

OH fire suppression rough-in.

Excavation 1.jpg

Interior wall framing progress.