top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Dec 18, 2025
THIS WEEK'S ACCOMPLISHMENT
- Placed 3 Board Form Finish columns on L-2.
- Continued all MEP OH rough-in and layout on L-1.
- Completed getting all interior walls for L-1 laid out.
- Resumed roof drain connections and installation of the French drain.
- Temp lighting and power connected to the building.
-

Temp lighting and power connected to new building.
NEXT WEEK'S ACTIVITIES
- Begin re-vegetation in Detention Pond, Water Quality Pond, and bus loop area mulch.
- Begin framing interior walls.
- Place 3 more Board Form Finish columns on L-2
- Continue OH MEP rough-in on L-1
- Continue fire suppression OH rough-in on L-1.

-
FRP for L-2 columns and walls.

Placed 3 Board Form Finish columns on L-2.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page