Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Dec 18, 2025

THIS WEEK'S ACCOMPLISHMENT

    Placed 3 Board Form Finish columns on L-2.
    Continued all MEP OH rough-in and layout on L-1.
    Completed getting all interior walls for L-1 laid out.
    Resumed roof drain connections and installation of the French drain.
    Temp lighting and power connected to the building.
Excavation 1.jpg

Temp lighting and power connected to new building.

NEXT WEEK'S ACTIVITIES

    Begin re-vegetation in Detention Pond, Water Quality Pond, and bus loop area mulch.
    Begin framing interior walls.
    Place 3 more Board Form Finish columns on L-2
    Continue OH MEP rough-in on L-1
    Continue fire suppression OH rough-in on L-1.
Excavation 1.jpg

FRP for L-2 columns and walls.

Excavation 1.jpg

Placed 3 Board Form Finish columns on L-2.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.