Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Aug 1, 2025

THIS WEEK'S ACCOMPLISHMENT

    Installed and Tied In New Fire Hydrant
    Continued Excavating for the Building Foundation, and Started Installing Base Material
    Continued Digging and Backfilling Storm Sewer Line SS-A
    Continued Digging and Backfilling Water Line WL-A
    Paved the Bus Loop and New Parking Areas
    New Water Line Passed Pressure Test Through WCID-17
Excavation 1.jpg

New Hydrant Install

NEXT WEEK'S ACTIVITIES

    Pave One Lane of Spillman Loop
    Conduct a Water Shutdown Tuesday at 4:00 AM, and Tie-In the New Water Line
    Continue Excavating the Building Foundation, and Installing Base Material
    Start Demo on the Existing Water Line
    Continue Digging and Backfilling Storm Sewer Line SS-A Crossing Through Lot P10
Excavation 1.jpg
    Stripe the Bus Loop, New Parking Areas, and One Lane of Spillman Loop

Foundation Pad Progress

Excavation 1.jpg

New Asphalt on The Bus Loop

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.