Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Aug 1, 2025
THIS WEEK'S ACCOMPLISHMENT
- Installed and Tied In New Fire Hydrant
- Continued Excavating for the Building Foundation, and Started Installing Base Material
- Continued Digging and Backfilling Storm Sewer Line SS-A
- Continued Digging and Backfilling Water Line WL-A
- Paved the Bus Loop and New Parking Areas
- New Water Line Passed Pressure Test Through WCID-17

New Hydrant Install
NEXT WEEK'S ACTIVITIES
- Pave One Lane of Spillman Loop
- Conduct a Water Shutdown Tuesday at 4:00 AM, and Tie-In the New Water Line
- Continue Excavating the Building Foundation, and Installing Base Material
- Start Demo on the Existing Water Line
- Continue Digging and Backfilling Storm Sewer Line SS-A Crossing Through Lot P10

- Stripe the Bus Loop, New Parking Areas, and One Lane of Spillman Loop
Foundation Pad Progress

New Asphalt on The Bus Loop
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.