top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Jul 25, 2025

THIS WEEK'S ACCOMPLISHMENT

    Completed Phase One Water and Roof Drain Pipe Insulation
    FRP Concrete Flume, 24" Headwall, and Sidewalk at the Bus Loop
    Completed Prep for Paving on the Bus Loop Road and Parking Areas
    Started Excavation of Building Foundation
    Continued Installation of Storm Drain, Line SS-A
    Started Installation of Water Line A
Excavation 1.jpg

FRP Curb and Flume at the Bus Loop

NEXT WEEK'S ACTIVITIES

    Paving of the Bus Loop and New Staff Parking Areas
    Continue working on Storm Drain Line SS-A and Begin Storm Drain Line SS-C
    Complete and Tie-In Water Line A
    Conduct water shutdowns July 29th, and August 1st at 4:00 AM.
    Continue Excavation of the Building Foundation
Excavation 1.jpg
    Complete Work in the Existing Building, and Return it to LTHS

SS-A Trench

Excavation 1.jpg

Foundation Pad Prep

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page