Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Jul 25, 2025
THIS WEEK'S ACCOMPLISHMENT
- Completed Phase One Water and Roof Drain Pipe Insulation
- FRP Concrete Flume, 24" Headwall, and Sidewalk at the Bus Loop
- Completed Prep for Paving on the Bus Loop Road and Parking Areas
- Started Excavation of Building Foundation
- Continued Installation of Storm Drain, Line SS-A
- Started Installation of Water Line A

FRP Curb and Flume at the Bus Loop
NEXT WEEK'S ACTIVITIES
- Paving of the Bus Loop and New Staff Parking Areas
- Continue working on Storm Drain Line SS-A and Begin Storm Drain Line SS-C
- Complete and Tie-In Water Line A
- Conduct water shutdowns July 29th, and August 1st at 4:00 AM.
- Continue Excavation of the Building Foundation

- Complete Work in the Existing Building, and Return it to LTHS
SS-A Trench

Foundation Pad Prep
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.