top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Sep 26, 2025

THIS WEEK'S ACCOMPLISHMENT

    Began Electrical underground rough-in
    Continued utilities work in Detention Pond #1
    Began installing 5x5 box in Detention Pond #1
    Inspection and testing for underground plumbing rough-in passed
    Placed new curbs in P10 and aprons for headwalls at Detention Pond #1 & #3
    Erected forms for poured form finish columns
Excavation 1.jpg

Utilities work continuing in Detention Pond #1

NEXT WEEK'S ACTIVITIES

    Continue FRP for grade beams and slab
    Place 3 columns
    Complete civil concrete and utilities in Detention Pond #1
    Continue work on biofiltration for Water Quality Pond #2
    Continue MEP rough-in of building pad
Excavation 1.jpg

Forms for columns erected

Excavation 1.jpg

Forms for walls and MEP rough-in progress

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page