Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Sep 26, 2025
THIS WEEK'S ACCOMPLISHMENT
- Began Electrical underground rough-in
- Continued utilities work in Detention Pond #1
- Began installing 5x5 box in Detention Pond #1
- Inspection and testing for underground plumbing rough-in passed
- Placed new curbs in P10 and aprons for headwalls at Detention Pond #1 & #3
- Erected forms for poured form finish columns

Utilities work continuing in Detention Pond #1
NEXT WEEK'S ACTIVITIES
- Continue FRP for grade beams and slab
- Place 3 columns
- Complete civil concrete and utilities in Detention Pond #1
- Continue work on biofiltration for Water Quality Pond #2
- Continue MEP rough-in of building pad

-
Forms for columns erected

Forms for walls and MEP rough-in progress
LOOK AHEAD SCHEDULE