Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Jan 29, 2026
THIS WEEK'S ACCOMPLISHMENT
- Inclement freezing weather from the weekend delayed all work from Monday and into Wednesday.
- Continued L-2 structural steel progress.
- Started installing metal decking for new roof work.
- Continued all MEP OH rough-in on L-1.
-
-

Structural steel progress on L-2.
NEXT WEEK'S ACTIVITIES
- Complete L-2 structural steel.
- Begin new roofing work.
- Complete interior wall layout on L-2.
- Install remaining L-1 HM door frames.
- Continue MEP OH rough-in on L-1.

- Continue exterior wall sheathing on L-1.
Exterior wall sheathing.

L-2 still frozen on Wednesday morning from weekend weather.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.