top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Jan 29, 2026

THIS WEEK'S ACCOMPLISHMENT

    Inclement freezing weather from the weekend delayed all work from Monday and into Wednesday.
    Continued L-2 structural steel progress.
    Started installing metal decking for new roof work.
    Continued all MEP OH rough-in on L-1.
Excavation 1.jpg

Structural steel progress on L-2.

NEXT WEEK'S ACTIVITIES

    Complete L-2 structural steel.
    Begin new roofing work.
    Complete interior wall layout on L-2.
    Install remaining L-1 HM door frames.
    Continue MEP OH rough-in on L-1.
Excavation 1.jpg
    Continue exterior wall sheathing on L-1.

Exterior wall sheathing.

Excavation 1.jpg

L-2 still frozen on Wednesday morning from weekend weather.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page