top of page


Weekly Project Update
Lake Travis High School Science Wing Addition

Jay McGilton
Oct 2, 2025
THIS WEEK'S ACCOMPLISHMENT
- Continued underground MEP Rough-In.
- Embeds for columns delivered.
- Placement of first 3 columns completed.
- Civil concrete completed for headwalls.
- Began installing biofiltration system in WQ#2.
- Completed installation of 5x5 box in Detention Pond #1.

MEP Rough-In continues to make progress
NEXT WEEK'S ACTIVITIES
- Place 3 more columns.
- Place the remaining grade beams in Area A.
- Continue underground MEP Rough-In.
- Pre-con meeting for Landscaping and Waterproofing.
- Continue work in Detention Pond #1 and WQ#2.

-
Rebar going in for grade beam placement

Biofiltration being installed in WQ#2
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page