Weekly Project Update

Lake Travis High School Science Wing Addition

Placeholder

Jay McGilton

Oct 2, 2025

THIS WEEK'S ACCOMPLISHMENT

    Continued underground MEP Rough-In.
    Embeds for columns delivered.
    Placement of first 3 columns completed.
    Civil concrete completed for headwalls.
    Began installing biofiltration system in WQ#2.
    Completed installation of 5x5 box in Detention Pond #1.
Excavation 1.jpg

MEP Rough-In continues to make progress

NEXT WEEK'S ACTIVITIES

    Place 3 more columns.
    Place the remaining grade beams in Area A.
    Continue underground MEP Rough-In.
    Pre-con meeting for Landscaping and Waterproofing.
    Continue work in Detention Pond #1 and WQ#2.
Excavation 1.jpg

Rebar going in for grade beam placement

Excavation 1.jpg

Biofiltration being installed in WQ#2

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.