top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Manor ISD Kitchen Serving Lines (Manor High School)

Placeholder

Stephen Bates

THIS WEEK'S ACCOMPLISHMENT

    Overhead doors installed
    Vinyl flooring installed
    Texture and paint completed on cafeteria wall
    Ceiling grid complete
    Grilles and lights set ready for inspections
    Old kitchen equipment moved in
Excavation 1.jpg

Vinyl flooring installed

NEXT WEEK'S ACTIVITIES

    Above ceiling inspections
    Set serving lines
    Hook up all equipment
    Fix trim at OH doors
    MEP final inspections
Excavation 1.jpg
    Final clean

Texture, paint and ceiling tile complete on cafeteria side

Excavation 1.jpg

Serving line equipment installing

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page