Weekly Project Update

Manor ISD Kitchen Serving Lines (Manor High School)

Placeholder

Stephen Bates

THIS WEEK'S ACCOMPLISHMENT

    All rebar inspected and concrete tested by testing labs
    Concrete pour back complete
    New serving line equipment laid out and ready for tile and vinyl flooring
    Framing and wall rough inspection passed
    Wall board installation in progress
    Tile started on walls and floors
Excavation 1.jpg

Concrete pour back complete

NEXT WEEK'S ACTIVITIES

    Continue wall tile
    Install overhead doors
    Finish installing wallboard
    Start tape and float
    Install Vinyl flooring
Excavation 1.jpg
    Get back area ready for above ceiling inspection and start tile

Wall board and wall tile started

Excavation 1.jpg

Floor tile started

LOOK AHEAD SCHEDULE