top of page


Weekly Project Update
Manor New Tech High School

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Tied steel reinforcement cages for the 2' and 3' diameter piers.
- Drilled, Inspected and poured 10 concrete piers along the south end of the building.
- Drilled inspected and poured 6 of 10 piers on the north side of the building
-
-

Pouring concrete into a pier using a tremie to issue even aggregate distribution.
NEXT WEEK'S ACTIVITIES
- Continue drilling piers
- Install the main storm drain lines on the west side of the building connecting to the existing pond.
-
-
-

-
Lowering the steel reinforcement cage down into the pier hole so concrete can be placed.

Tying the steel rebar cages for the 3' diameter piers.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page