THIS WEEK'S ACCOMPLISHMENT

    Tied steel reinforcement cages for the 2' and 3' diameter piers.
    Drilled, Inspected and poured 10 concrete piers along the south end of the building.
    Drilled inspected and poured 6 of 10 piers on the north side of the building
Excavation 1.jpg

Pouring concrete into a pier using a tremie to issue even aggregate distribution.

NEXT WEEK'S ACTIVITIES

    Continue drilling piers
    Install the main storm drain lines on the west side of the building connecting to the existing pond.
Excavation 1.jpg

Lowering the steel reinforcement cage down into the pier hole so concrete can be placed.

Excavation 1.jpg

Tying the steel rebar cages for the 3' diameter piers.