THIS WEEK'S ACCOMPLISHMENT
- Demo completed at both locations
- Plumbing rough completed
- Electrical rough completed
- Electrical and Plumbing rough inspections passed
- Walls insulated and covered up at Softball
- Exterior water shut off repaired

Plumbing and electrical rough completed at Baseball
NEXT WEEK'S ACTIVITIES
- Patch CMU at baseball concessions
- Paint at softball and baseball concessions
- Prep and seal concrete where old millwork was
- Install equipment that is available
- Final clean

-
Plumbing and electrical rough completed at Softball

Walls patched and ready for paint