THIS WEEK'S ACCOMPLISHMENT
- Sheet rock started
- Insulation on plumbing pipes inspected last week
- Rough in electrical continues
- Framing new walls 80% complete waiting on replacing damaged sheet rock issue
- Duct work installation 80% complete. Waiting on thru wall issue
- Survived the winter storm and power outages.

Blocking for lockers and toilet accessories
NEXT WEEK'S ACTIVITIES
- Steel beam for partition to arrvie and install.
- Sheet rock to continue
- Blocking to continue
- Electrical and low voltage to continue
- Pipe insulation should complete

- Partial duct installation should complete.
Insulation of plumbing pipes continues

Sheet rock started on hallway walls so tops (tunnel lids) can frame next week.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.