Weekly Project Update
MNTHS

Richard Huddleston
THIS WEEK'S ACCOMPLISHMENT
- Installed void form boxes on grid lines 1 & I
- Installed vapor barrier, rebar, and 2nd side of beam forms on grid lines 1 & I
- Poured concrete in grade beams on grid lines 1 & I.
-
-
-

Pre- pour photo of grid line 1
NEXT WEEK'S ACTIVITIES
- Remove forms from grade beams on grid lines 1 & I
- Install void boxes, vapor barrier and rebar on grid line A
- Pour concrete on grid line A.
-
-

-
1st grade beam pour in progress.

Continuing concrete pour on grid line I.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.