Weekly Project Update

Murchison ES restroom renovation

Placeholder

Sid Wegert

THIS WEEK'S ACCOMPLISHMENT

    All demo complete
    Electrical and plumbing rough-in complete in faculty and nurse restrooms
    Faculty and Nurse restrooms sheetrocked
    Masonry build-back on CMU walls started
    Plumbing rough in 90% complete in Gang restroom A
    Electrical rough in complete in gang restrooms B and C
Excavation 1.jpg

Nurse restroom sheetrocked

NEXT WEEK'S ACTIVITIES

    Begin installing tile in nurse and faculty restrooms
    Complete electrical and plumbing rough-in gang restroom A
    Rough-in plumbing gang restroom C and B
    Complete all electrical rough-in
    Begin sheetrocking gang restrooms and hallways in front of restrooms
Excavation 1.jpg

Faculty restrooms rough in complete with sheetrock installed

Excavation 1.jpg

Gang restroom A plumbing rough and CMU put-back

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.