top of page


Weekly Project Update
Murchison ES restroom renovation

Sid Wegert
THIS WEEK'S ACCOMPLISHMENT
- All demo complete
- Electrical and plumbing rough-in complete in faculty and nurse restrooms
- Faculty and Nurse restrooms sheetrocked
- Masonry build-back on CMU walls started
- Plumbing rough in 90% complete in Gang restroom A
- Electrical rough in complete in gang restrooms B and C

Nurse restroom sheetrocked
NEXT WEEK'S ACTIVITIES
- Begin installing tile in nurse and faculty restrooms
- Complete electrical and plumbing rough-in gang restroom A
- Rough-in plumbing gang restroom C and B
- Complete all electrical rough-in
- Begin sheetrocking gang restrooms and hallways in front of restrooms

-
Faculty restrooms rough in complete with sheetrock installed

Gang restroom A plumbing rough and CMU put-back
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.
bottom of page