Weekly Project Update
PARK CREST MS RESTROOM MODERNIZATION

Dakota Zimmerman
Jul 7, 2025
THIS WEEK'S ACCOMPLISHMENT
- Tape & Floated ceilings in Main corridor, A-B Cross corridor, & C Hall restrooms.
- Installed new Grills for AC & Exhaust in all project restrooms.
- Installed blocking & Dense Shield on Chase wall in B Hall restroom.
- Finished installing Dense Shield in C Hall restroom.
- Installed new light fixtures in Main Corridor restrooms.
- Installed new floor drain in C Hall Boys restroom.

Installed new Floor Drain in C Hall
NEXT WEEK'S ACTIVITIES
- Finish installing new light fixtures in all project restrooms.
- Spray Texture on ceilings in Main corridor, A-B Cross corridor, & C Hall restrooms.
- Install new floor drain in Main Corridor Boys restroom.
- Prep floors & walls for Tile in all project restrooms & start installing Tile in B Hall restrooms.
- Install Speakers in Ceilings in Main corridor, A-B Cross corridor, & C Hall restrooms.

- Repair Trap Primer & replace Shut off valve in C Hall.
Installed Blocking in B Hall Restroom.

Installing new Grills for HVAC in C Hall
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.