Weekly Project Update
PARK CREST MS RESTROOM MODERNIZATION

Dakota Zimmerman
Jun 30, 2025
THIS WEEK'S ACCOMPLISHMENT
- Remove existing flush valves & cap off & prep for new fixtures in B Hall, A-B Cross, Ban/Theatre, & Main Corridor restrooms.
- Roughed in plumbing for B Hall restroom.
- Installed Dense Shield in A-B Cross corridor & C Hall.
- Finished installing Sheetrock on Ceilings.
- Raised up Floor Drains & Patched back concrete in Ban/Theatre, Main Corridor, B-Hall, A-B Cross & C Hall restrooms.
-

Extending Plumbing lines for Toilets in Band/Theatre
NEXT WEEK'S ACTIVITIES
- Tape & Float Ceilings in all project restrooms.
- Finish installing Dense Shield in C Hall restroom and install blocking & Sheetrock on Chase wall in B Hall restroom.
- Prep Floors & Walls for Tile in all project restrooms.
- Install new Grills & Exhaust in all project restrooms.
-

-
Raised up Floor Drain in C Hall

Installed Dense Shield in C Hall
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.