THIS WEEK'S ACCOMPLISHMENT

    Remove existing flush valves & cap off & prep for new fixtures in B Hall, A-B Cross, Ban/Theatre, & Main Corridor restrooms.
    Roughed in plumbing for B Hall restroom.
    Installed Dense Shield in A-B Cross corridor & C Hall.
    Finished installing Sheetrock on Ceilings.
    Raised up Floor Drains & Patched back concrete in Ban/Theatre, Main Corridor, B-Hall, A-B Cross & C Hall restrooms.
Excavation 1.jpg

Extending Plumbing lines for Toilets in Band/Theatre

NEXT WEEK'S ACTIVITIES

    Tape & Float Ceilings in all project restrooms.
    Finish installing Dense Shield in C Hall restroom and install blocking & Sheetrock on Chase wall in B Hall restroom.
    Prep Floors & Walls for Tile in all project restrooms.
    Install new Grills & Exhaust in all project restrooms.
Excavation 1.jpg

Raised up Floor Drain in C Hall

Excavation 1.jpg

Installed Dense Shield in C Hall

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page