Weekly Project Update
PARK CREST MS RESTROOM MODERNIZATION

Dakota Zimmerman
Jul 14, 2025
THIS WEEK'S ACCOMPLISHMENT
- Installed new Floor Drain in Main Corridor Boy's and finished adjusting drains & clean outs for Floor Tile in all project restrooms
- Finished installing new Light Fixtures in all restrooms except A-B Cross Corridor Boy's.
- Replaced bad Trap Primer & Shutoff Valve for C Hall.
- Prep floors for Floor Tile for B Hall & C Hall restrooms.
- Delivered Tile & Grout.
-

Adjusted floor clean out A-B cross corridor Boy's
NEXT WEEK'S ACTIVITIES
- Take down Temp Walls.
- Deliver new Access Panels.
- Deliver new Sinks for project restrooms.
- Install Floor & Wall Tile in C Hall & B Hall restrooms.
- Install new Toilets, Urinals, & Sinks in C Hall & B Hall restrooms.

- Re-Install Speakers in C Hall restrooms.
Prepping floors for Floor Tile in C Hall Girls

New Light Fixtures A-B cross corridor Girls
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.