Weekly Project Update

PARK CREST MS RESTROOM MODERNIZATION

Placeholder

Dakota Zimmerman

Jul 14, 2025

THIS WEEK'S ACCOMPLISHMENT

    Installed new Floor Drain in Main Corridor Boy's and finished adjusting drains & clean outs for Floor Tile in all project restrooms
    Finished installing new Light Fixtures in all restrooms except A-B Cross Corridor Boy's.
    Replaced bad Trap Primer & Shutoff Valve for C Hall.
    Prep floors for Floor Tile for B Hall & C Hall restrooms.
    Delivered Tile & Grout.
Excavation 1.jpg

Adjusted floor clean out A-B cross corridor Boy's

NEXT WEEK'S ACTIVITIES

    Take down Temp Walls.
    Deliver new Access Panels.
    Deliver new Sinks for project restrooms.
    Install Floor & Wall Tile in C Hall & B Hall restrooms.
    Install new Toilets, Urinals, & Sinks in C Hall & B Hall restrooms.
Excavation 1.jpg
    Re-Install Speakers in C Hall restrooms.

Prepping floors for Floor Tile in C Hall Girls

Excavation 1.jpg

New Light Fixtures A-B cross corridor Girls

LOOK AHEAD SCHEDULE