Weekly Project Update
PARK CREST MS RESTROOM MODERNIZATION

Dakota Zimmerman
Jul 21, 2025
THIS WEEK'S ACCOMPLISHMENT
- Prepped Floors for Floor Tile in A-B, Main Corridor, & Band Theatre/Corridor
- Installed Floor & Wall Tile in C Hall & Grouted and completed Wall & Floor Tile in B Hall Restroom.
- Installed Occupancy Sensors in Band/Theatre, Main Corridor, B Hall & A-B Cross Corridor
- Delivered Sinks for all Project Restrooms
- Delivered Access Panels
-

B Hall Boy's Tile
NEXT WEEK'S ACTIVITIES
- Complete Wall & Floor Tile in all project restrooms
- Install Sinks, Water Fountains, Toilets, & Urinals in B Hall, C Hall, A-B Cross Corridor, & Main Corridor Restrooms.
- Install Hand Dryers, E Lights, & complete lighting controls in all project restrooms.
- Install Access Panel in all project restrooms.
-

-
Installing Wall Tile in C Hall Girls

B Hall Vestibule Tile
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.