THIS WEEK'S ACCOMPLISHMENT

    Prepped Floors for Floor Tile in A-B, Main Corridor, & Band Theatre/Corridor
    Installed Floor & Wall Tile in C Hall & Grouted and completed Wall & Floor Tile in B Hall Restroom.
    Installed Occupancy Sensors in Band/Theatre, Main Corridor, B Hall & A-B Cross Corridor
    Delivered Sinks for all Project Restrooms
    Delivered Access Panels
Excavation 1.jpg

B Hall Boy's Tile

NEXT WEEK'S ACTIVITIES

    Complete Wall & Floor Tile in all project restrooms
    Install Sinks, Water Fountains, Toilets, & Urinals in B Hall, C Hall, A-B Cross Corridor, & Main Corridor Restrooms.
    Install Hand Dryers, E Lights, & complete lighting controls in all project restrooms.
    Install Access Panel in all project restrooms.
Excavation 1.jpg

Installing Wall Tile in C Hall Girls

Excavation 1.jpg

B Hall Vestibule Tile

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page