Weekly Project Update

PF LTC

Placeholder

Nathan Stanford

Dec 18, 2025

THIS WEEK'S ACCOMPLISHMENT

    More demountable walls installed
    Power and data feeding into demountable walls
    More flooring installing
    More special ceilings and accompanying lights installing.
    Sheet rock demo, blocking and patch back for changes occuring
    Last of floor tile installing
Excavation 1.jpg

Doors and hardware installing

NEXT WEEK'S ACTIVITIES

    Continue on demountable walls
    Continue on special lights install
    Last of carpet installed, except for that on hold waiting on 08 welding changes.
    Continue on demo sheet rock and add blocking for 08 changes
    Waiting on outside air and venting in riser room changes to be approved.
Excavation 1.jpg
    Base on floor starts.

Large hole pending for big screen change order. Waiting on welding

Excavation 1.jpg

Some screen in rooms installing. Part of DSI plans.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.