THIS WEEK'S ACCOMPLISHMENT
- More demountable walls installed
- Power and data feeding into demountable walls
- More flooring installing
- More special ceilings and accompanying lights installing.
- Sheet rock demo, blocking and patch back for changes occuring
- Last of floor tile installing

Doors and hardware installing
NEXT WEEK'S ACTIVITIES
- Continue on demountable walls
- Continue on special lights install
- Last of carpet installed, except for that on hold waiting on 08 welding changes.
- Continue on demo sheet rock and add blocking for 08 changes
- Waiting on outside air and venting in riser room changes to be approved.

- Base on floor starts.
Large hole pending for big screen change order. Waiting on welding

Some screen in rooms installing. Part of DSI plans.
LOOK AHEAD SCHEDULE