Weekly Project Update
Pf LTC

Nathan Stanford
Nov 28, 2025
THIS WEEK'S ACCOMPLISHMENT
- More demountable walls installed
- More lights and plugs installed
- Plumbing set out started
- Special ceilings installation started
- Lots of cable being installed
- UPS delays finalized. Can start up again.

Accent tile and grout in bathrooms
NEXT WEEK'S ACTIVITIES
- Special ceilings continue
- More lights and plugs install
- Plumbing set out of special LAV's continue
- More demountable walls continue
- Starting coordination meeting for AV extra work and pricing.

- Millwork completes
Special ceilings starting to install

Demountable wall installation continues
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.