Weekly Project Update
PF LTC

Nathan Stanford
Dec 18, 2025
THIS WEEK'S ACCOMPLISHMENT
- More4 demountable walls install
- Power and data to demountable walls installing
- Flooring installing
- Paint touch up installing
- Last of a/c grilles installing. Pending changes from engineer
- Special ceilings and lights around them installing.

Doors and hardware starting to install
NEXT WEEK'S ACTIVITIES
- More demountable walls install
- Data and power feed to demountable walls continues
- Last of flooring installs, pending DSI/Owner changes getting done. Holding off flooring here.
- ISD UPS continues to install
- Hardware continues to install

-
Large hole pending welding waiting on DSI large screen

Some smaller screens in rooms installing.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.