Weekly Project Update

PF LTC

Placeholder

Nathan Stanford

Dec 18, 2025

THIS WEEK'S ACCOMPLISHMENT

    More4 demountable walls install
    Power and data to demountable walls installing
    Flooring installing
    Paint touch up installing
    Last of a/c grilles installing. Pending changes from engineer
    Special ceilings and lights around them installing.
Excavation 1.jpg

Doors and hardware starting to install

NEXT WEEK'S ACTIVITIES

    More demountable walls install
    Data and power feed to demountable walls continues
    Last of flooring installs, pending DSI/Owner changes getting done. Holding off flooring here.
    ISD UPS continues to install
    Hardware continues to install
Excavation 1.jpg

Large hole pending welding waiting on DSI large screen

Excavation 1.jpg

Some smaller screens in rooms installing.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.