Weekly Project Update
Pf LTC

Nathan Stanford
Dec 11, 2025
THIS WEEK'S ACCOMPLISHMENT
- More demountable walls
- More power and data into demountable walls
- Special ceilings continue
- Electrical rough in continues for lots of changes.
- UPS delay being worked on
- Camera delay being worked on

Demountable walls in "C" have begun
NEXT WEEK'S ACTIVITIES
- Demountable walls contiue
- Changes due to DSI adds being worked on. Tearing open finished walls
- Changes due to cameras being worked on
- Low voltage wiring continue. Miles and miles of cable.
- Flooring starts back up.

- Plumbing set out completes
Corridors completed with lights up. Floor in and protected

Demo for added screen has begun.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.