top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

Pf LTC

Placeholder

Nathan Stanford

Dec 5, 2025

THIS WEEK'S ACCOMPLISHMENT

    More data wiring run
    More lights and plugs run
    More demountable walls installed
    Start some demo for 08 changes
    Starting changes for UPS and camera changes
    Re-bar in generator pad
Excavation 1.jpg

Generator pad

NEXT WEEK'S ACTIVITIES

    Pour generator pad
    Pull more data wiring
    UPS changes drawing due so this work can start
    More power and lights install
    More special ceilings install
Excavation 1.jpg
    Meeting about 08 schedule impact.

Accent tile with drinking fountain

Excavation 1.jpg

Glass in demountable walls

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page