Weekly Project Update
Pf LTC

Nathan Stanford
Dec 5, 2025
THIS WEEK'S ACCOMPLISHMENT
- More data wiring run
- More lights and plugs run
- More demountable walls installed
- Start some demo for 08 changes
- Starting changes for UPS and camera changes
- Re-bar in generator pad

Generator pad
NEXT WEEK'S ACTIVITIES
- Pour generator pad
- Pull more data wiring
- UPS changes drawing due so this work can start
- More power and lights install
- More special ceilings install

- Meeting about 08 schedule impact.
Accent tile with drinking fountain

Glass in demountable walls
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.