Weekly Project Update
PfISD LTC

Nathan Stanford
Aug 18, 2025
THIS WEEK'S ACCOMPLISHMENT
- More sheet rock "C" and "B" where not on hold
- Pulling large wire for new electrical gear
- Wrapping up last of duct work 96%
- Compact water proof ditch on exterior North and West sides
- Pulling small wire to electrical boxes from breaker boxes
- Insulation on last inspected duct work.

Largest room "Professional Development" starting to sheet rock.
NEXT WEEK'S ACTIVITIES
- Windows should ship to job
- Getting ready for roof top unit curbs to arrive
- Continue to sheet rock where framing inspections have passed
- Tape and float where screw inspections have passed
- Cable tray hangers should complete

- Pour back concrete of water proofing ditch.
Bathroom ceiling framing. Wall still on holf for changed sink

Large wire for feeds to electrical rooms from main gear.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.