top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

PfISD LTC

Placeholder

Nathan Stanford

Aug 18, 2025

THIS WEEK'S ACCOMPLISHMENT

    More sheet rock "C" and "B" where not on hold
    Pulling large wire for new electrical gear
    Wrapping up last of duct work 96%
    Compact water proof ditch on exterior North and West sides
    Pulling small wire to electrical boxes from breaker boxes
    Insulation on last inspected duct work.
Excavation 1.jpg

Largest room "Professional Development" starting to sheet rock.

NEXT WEEK'S ACTIVITIES

    Windows should ship to job
    Getting ready for roof top unit curbs to arrive
    Continue to sheet rock where framing inspections have passed
    Tape and float where screw inspections have passed
    Cable tray hangers should complete
Excavation 1.jpg
    Pour back concrete of water proofing ditch.

Bathroom ceiling framing. Wall still on holf for changed sink

Excavation 1.jpg

Large wire for feeds to electrical rooms from main gear.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.