Weekly Project Update
PfISD LTC

Nathan Stanford
Jul 9, 2025
THIS WEEK'S ACCOMPLISHMENT
- Base sheet 100% on roof. Started top sheet
- More electrical, framing, and mechanical rough in section "C" area
- Sheet rock started in "A" area
- Started manhole work for deep sewer line.
- Sprinkler high work under deck 90% complete. Inspection due next week.
- Main electrical room painted so gear can start to install early next month.

Black on roof is base coat complete
NEXT WEEK'S ACTIVITIES
- Friday more inspections due on "C" area. Wall framing and electrical wall rough
- Top coat on roofing continues weather permitting
- Sheet rock continues in "A" area
- Manhole work should inspect and complete
- More duct in A&C areas. Start duct in "B" area.

- Waiting on PfISD to solidify changes to AV, low voltage, and other changes
White area on roof is top coat starting to install

Section "A" Asst super area with demountable wall above. This is how the final look will feel
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.