THIS WEEK'S ACCOMPLISHMENT

    Base sheet 100% on roof. Started top sheet
    More electrical, framing, and mechanical rough in section "C" area
    Sheet rock started in "A" area
    Started manhole work for deep sewer line.
    Sprinkler high work under deck 90% complete. Inspection due next week.
    Main electrical room painted so gear can start to install early next month.
Excavation 1.jpg

Black on roof is base coat complete

NEXT WEEK'S ACTIVITIES

    Friday more inspections due on "C" area. Wall framing and electrical wall rough
    Top coat on roofing continues weather permitting
    Sheet rock continues in "A" area
    Manhole work should inspect and complete
    More duct in A&C areas. Start duct in "B" area.
Excavation 1.jpg
    Waiting on PfISD to solidify changes to AV, low voltage, and other changes

White area on roof is top coat starting to install

Excavation 1.jpg

Section "A" Asst super area with demountable wall above. This is how the final look will feel