Weekly Project Update
PFISD - Safety and Security Upgrades - PHASE 2

Keith Farrell
THIS WEEK'S ACCOMPLISHMENT
- Installed Wood Doors and Hardware at Dearing Elementary F1, F5, & F6. (Doors held open with Mag Holds)
- Installed Wood Doors and Hardware at Barron Elementary B5, B7, & B8. (Doors held open with Mag Holds)
- Delivered Wood Doors and Hardware for Pflugerville & Riojas Elementary.
- Installed Hardware on Wood Doors (Prep for Install) at Barron, Brookhollow, Caldwell, Pflugerville, Riojas, & Rowe Lane Elementary.
- Installed New Lockdown Button at Barron, Dearing, Delco, Highland Park, Rowe Lane, & Wieland Elementary.
- Wired up New ACP, Mag Holds, & Powered up Mag Holds at Dearing Elementary.

New Wood Doors at Dearing Elementary F1 (Doors held open with Mag Holds)
NEXT WEEK'S ACTIVITIES
- Install Wood Doors and Hardware at Delco, Pflugerville Elementary.
- Finish installing Wood Doors and Hardware at Barron Elementary. (B3, B4, B6, & B9)
- Receive Wood Doors and Hardware for River Oaks, Springhill, & Windermere Elementary.
- Start Installing Wood Doors and Hardware at Dessau & Rowe Lane Elementary.
- Tie Into Existing System and Power up Mag Holds for Wood Doors at Brookhollow Elementary.

- Install AI-Phone & Master Station at Dessau & Northwest Elementary.
New Wood Doors at Barron Elementary B8 (Doors held open with Mag Holds)

Installing New Lockdown Button at Dearing Elementary
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.