Weekly Project Update

PFISD LTC Data Center

Placeholder

Nathan Stanford

Jul 24, 2025

THIS WEEK'S ACCOMPLISHMENT

    Continue sheet rock and exterior wall insulation in "A" section
    Continue framing and installing electrical and mechanical in "B" section
    Continue sheet rock at demountable walls in "C" section
    Started waterproofing ditch for below grade exterior wall outside where finish floor is below grade.
    Finished top coat of roofing
    Large conduits from main existing gear room to main electrical room inside continues.
Excavation 1.jpg

Tape and float high wall that passed screw inspection. Insulate walls that passed framing

NEXT WEEK'S ACTIVITIES

    More inspections in different sections on mechanical, electrical, framing, insulation, and sheetrock.
    Waterproofing starts outside.
    Metal parapet cap due to start
    Insulation and sheet rock continues in all 3 sections.
    HWH piping start to install now we have a confirmed selection
Excavation 1.jpg
    Duct insulation starts on A & B areas that have passed inspecton

Sheet rock installs on area A where framing inspection has passed

Excavation 1.jpg

Ditch to access for waterproofing floor area below grade to help prevent moisture intrusion

LOOK AHEAD SCHEDULE