Weekly Project Update
PFISD LTC Data Center

Nathan Stanford
Jul 24, 2025
THIS WEEK'S ACCOMPLISHMENT
- Continue sheet rock and exterior wall insulation in "A" section
- Continue framing and installing electrical and mechanical in "B" section
- Continue sheet rock at demountable walls in "C" section
- Started waterproofing ditch for below grade exterior wall outside where finish floor is below grade.
- Finished top coat of roofing
- Large conduits from main existing gear room to main electrical room inside continues.

Tape and float high wall that passed screw inspection. Insulate walls that passed framing
NEXT WEEK'S ACTIVITIES
- More inspections in different sections on mechanical, electrical, framing, insulation, and sheetrock.
- Waterproofing starts outside.
- Metal parapet cap due to start
- Insulation and sheet rock continues in all 3 sections.
- HWH piping start to install now we have a confirmed selection

- Duct insulation starts on A & B areas that have passed inspecton
Sheet rock installs on area A where framing inspection has passed

Ditch to access for waterproofing floor area below grade to help prevent moisture intrusion
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.