top of page
BB-construction logo_PMS_edited.png

Weekly Project Update

PfISD LTC

Placeholder

Nathan Stanford

Aug 7, 2025

THIS WEEK'S ACCOMPLISHMENT

    Continued electrical rough in where we can while waiting on more changes to be issued.
    Duct work continues to be installed. 95% waiting on roof top units to continue.
    Framing and sheet rock progressing where we are not on hold on changes.
    Tape and float work continues on walls up high.
    Preparations underway for large electrical gear ready to upgrade to new in about 3 weeks.
    More city inspection due Friday to continue more sheet rock.
Excavation 1.jpg

Bathroom construction on hold pending changes.

NEXT WEEK'S ACTIVITIES

    Continue work for large electrical gear change over.
    More electrical wall and ceiling rough in work. Pending some changes getting approved.
    Once different section pass inspection more tape and float up high to continue tape and float.
    Framing metal hard lid ceilings continue pending changes.
    Cable tray hangers continue.
Excavation 1.jpg
    Start to work on pour back of waterproofing ditch.

Warehouse area framing and sheet rock.

Excavation 1.jpg

Second area "C" hanging demountable walls ready to start tape and float.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.

bottom of page