Weekly Project Update
PfISD LTC

Nathan Stanford
Aug 7, 2025
THIS WEEK'S ACCOMPLISHMENT
- Continued electrical rough in where we can while waiting on more changes to be issued.
- Duct work continues to be installed. 95% waiting on roof top units to continue.
- Framing and sheet rock progressing where we are not on hold on changes.
- Tape and float work continues on walls up high.
- Preparations underway for large electrical gear ready to upgrade to new in about 3 weeks.
- More city inspection due Friday to continue more sheet rock.

Bathroom construction on hold pending changes.
NEXT WEEK'S ACTIVITIES
- Continue work for large electrical gear change over.
- More electrical wall and ceiling rough in work. Pending some changes getting approved.
- Once different section pass inspection more tape and float up high to continue tape and float.
- Framing metal hard lid ceilings continue pending changes.
- Cable tray hangers continue.

- Start to work on pour back of waterproofing ditch.
Warehouse area framing and sheet rock.

Second area "C" hanging demountable walls ready to start tape and float.
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.