Weekly Project Update
PfISD LTC

Nathan Stanford
Feb 19, 2026
THIS WEEK'S ACCOMPLISHMENT
- Final clean
- Low voltage continues waiting on network
- Electrical and Mechanical Finals
- Last of demountable walls getting wired
- Plumbing inspection Friday pending gas meter install
- Walk with Fire Marshal to discuss some open issues

Computer room complete. Waiting on PfISD equipment install
NEXT WEEK'S ACTIVITIES
- Fire final inspection scheduled
- Complete Bb punch list
- Owners punch walk
- Finish cleaning
- Owners training

- Possibly Building final TCO inspection pending a lot of paperwork
PfISD equipment ready to install.

Hallways completed
LOOK AHEAD SCHEDULE
Click on document icon below to review the detailed Look Ahead Schedule.