THIS WEEK'S ACCOMPLISHMENT

    Final clean
    Low voltage continues waiting on network
    Electrical and Mechanical Finals
    Last of demountable walls getting wired
    Plumbing inspection Friday pending gas meter install
    Walk with Fire Marshal to discuss some open issues
Excavation 1.jpg

Computer room complete. Waiting on PfISD equipment install

NEXT WEEK'S ACTIVITIES

    Fire final inspection scheduled
    Complete Bb punch list
    Owners punch walk
    Finish cleaning
    Owners training
Excavation 1.jpg
    Possibly Building final TCO inspection pending a lot of paperwork

PfISD equipment ready to install.

Excavation 1.jpg

Hallways completed