THIS WEEK'S ACCOMPLISHMENT
- Set Roof Top Units
- Waiting on LAV changes approval to close up walls
- Sheet rock screw inspection area "C"
- Final wall insulation inspection "B"
- Most of parapet cap installed
- Rough in of electrical continues. Backing up for changes.

Parapet cap install almost complete
NEXT WEEK'S ACTIVITIES
- More inspections
- More sheet rock install
- More electrical changes being made and installed
- Last of duct installed. Exception is CRAC area waiting on paint first.
- Getting ready for roof top units start up next week. Electrical and Mechanical.

- Tape and float re-starts after added EJ's
Main expansion joint at roof nearing completion

Roof Top Units installed. Prepping for start up soon.