Weekly Project Update

PfISD LTC

Placeholder

Nathan Stanford

Nov 7, 2025

THIS WEEK'S ACCOMPLISHMENT

    More ceramic tile
    More carpet
    More ceiling grid
    Special ceiling clouds framing
    Started turning on some lights and plugs
    1st coat of interior paint 95%
Excavation 1.jpg

More carpet installing.

NEXT WEEK'S ACTIVITIES

    More ceramic tile
    More carpet
    More sealing floors
    More ceiling grid continues
    Exterior painting 90%
Excavation 1.jpg
    Electrical lights and plugs continues.

More tile installing

Excavation 1.jpg

Special ceiling framing installing.