Weekly Project Update

PfISD LTC

Placeholder

Nathan Stanford

Oct 6, 2025

THIS WEEK'S ACCOMPLISHMENT

    Tape and float of ceilings started "B" section
    Painting of "A" section started
    A/C grilles in section "C" started
    CRAC units set
    Ceiling grid started "C"
    Units prepped for start up.
Excavation 1.jpg

Sheet rock ceilings installing

NEXT WEEK'S ACTIVITIES

    Ceiling grid in "A" starts
    More A/C grilles in grid as ceilings progress
    Wiring pulled thru conduit all over
    Plumber returns for hot water heater set out
    Power wash exterior continues. Painting outside starts
Excavation 1.jpg
    Tape and float continue in "B" section.

Sheet rock on walls now 95%

Excavation 1.jpg

CRAC units set in data room. Duct being run in room

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.