Weekly Project Update
PfISD LTC

Nathan Stanford
Oct 6, 2025
THIS WEEK'S ACCOMPLISHMENT
- Tape and float of ceilings started "B" section
- Painting of "A" section started
- A/C grilles in section "C" started
- CRAC units set
- Ceiling grid started "C"
- Units prepped for start up.

Sheet rock ceilings installing
NEXT WEEK'S ACTIVITIES
- Ceiling grid in "A" starts
- More A/C grilles in grid as ceilings progress
- Wiring pulled thru conduit all over
- Plumber returns for hot water heater set out
- Power wash exterior continues. Painting outside starts

- Tape and float continue in "B" section.
Sheet rock on walls now 95%

CRAC units set in data room. Duct being run in room