THIS WEEK'S ACCOMPLISHMENT
- Continues framing in section "B"
- Continued duct and electrical in sections "B"
- Sheet rock and insulation in section "A" for city inspection
- Main electrical room painted and large gear started installing.
- Roof final top coat 95%
- All demountable wall framing 95% This was a lot!!

Main electrical room painted and heavy gear starting to install
NEXT WEEK'S ACTIVITIES
- More city framing and insulation inspections
- More electrical and mechanical city inspections
- All trades trying to finish rough in in last section "B" walls. Ceilings happen later.
- Roof metal coping work to start
- After insulation inspections more sheet rock can happen

- Anticipate high under deck sprinkler fire marshal inspection
Insulation on exterior walls where no windows were added

Roof top coat 95% complete. Metal coping due to start next week.