THIS WEEK'S ACCOMPLISHMENT

    Continues framing in section "B"
    Continued duct and electrical in sections "B"
    Sheet rock and insulation in section "A" for city inspection
    Main electrical room painted and large gear started installing.
    Roof final top coat 95%
    All demountable wall framing 95% This was a lot!!
Excavation 1.jpg

Main electrical room painted and heavy gear starting to install

NEXT WEEK'S ACTIVITIES

    More city framing and insulation inspections
    More electrical and mechanical city inspections
    All trades trying to finish rough in in last section "B" walls. Ceilings happen later.
    Roof metal coping work to start
    After insulation inspections more sheet rock can happen
Excavation 1.jpg
    Anticipate high under deck sprinkler fire marshal inspection

Insulation on exterior walls where no windows were added

Excavation 1.jpg

Roof top coat 95% complete. Metal coping due to start next week.