THIS WEEK'S ACCOMPLISHMENT

    More sheet rock areas B & C
    Windows and glass arrived
    Primary Electrical gear swap over started
    More insulation in walls area B
    Large feeder wires installed between panels and primary gear
    Small feeder wires continue between sub panels to switches and plugs
Excavation 1.jpg

Large room sheet rock 75%

NEXT WEEK'S ACTIVITIES

    Continue sheet rock
    Continue Electrical
    Roof curbs arrive
    Main gear swap over continues
    On hold waiting on submittals
Excavation 1.jpg
    On hold waiting on recently added changes to get priced and approved.

Windows install with glass

Excavation 1.jpg

Added walls to deck finally started

LOOK AHEAD SCHEDULE