THIS WEEK'S ACCOMPLISHMENT
- More sheet rock areas B & C
- Windows and glass arrived
- Primary Electrical gear swap over started
- More insulation in walls area B
- Large feeder wires installed between panels and primary gear
- Small feeder wires continue between sub panels to switches and plugs

Large room sheet rock 75%
NEXT WEEK'S ACTIVITIES
- Continue sheet rock
- Continue Electrical
- Roof curbs arrive
- Main gear swap over continues
- On hold waiting on submittals

- On hold waiting on recently added changes to get priced and approved.
Windows install with glass

Added walls to deck finally started