Weekly Project Update

PfISD LTC

Placeholder

Nathan Stanford

Jul 3, 2025

THIS WEEK'S ACCOMPLISHMENT

    Area A passed framing and electrical inspection on walls. This is a big step. Next area inspection 2 to 3 weeks out.
    Entire building passed Plumbing inspection in walls. This allows us to start insulation on pipes in walls.
    Electrical and mechanical continue to rough in areas B & C
    One side of sheet rock on furr downs (demountable walls) has started in A area. Lots of high work will take a lot of time to finish.
    Roofing base sheet 100% Beam and manufacturers base sheet inspection ok. Top sheet started.
    Last of blocking for folding partitions. All vendors ok with blocking and field check verifications except for FMG
Excavation 1.jpg

Folding partition blocking installed. Tracks ordered due late July

NEXT WEEK'S ACTIVITIES

    Top sheet on roof weather permitting. Parapet cap to start
    Continue to rough in mechanical and electrical in areas B & C
    Tape and float large electrical room. This will let us prepare for main gear swap out in August.
    Framing of furr downs and walls in B & C
    All large piping on sprinkler due to complete and inspect up high.
Excavation 1.jpg
    Manhole work should start.

All plumbing in walls passed inspection. Started insulation.

Excavation 1.jpg

Lots of duct and furr downs in area A.

LOOK AHEAD SCHEDULE

Click on document icon below to review the detailed Look Ahead Schedule.